Concrete Plant Park Emergency Tower Demolition

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will demolish three decommissioned concrete plant towers that have deteriorated and pose a public safety risk.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2023
Projected Completion Date: November 2023
Completion Date: October 2023

Procurement

Start Date: October 2023
Projected Completion Date: October 2024
Completion Date: January 2024

Construction

Start Date: June 2023
Projected Completion Date: September 2023
Completion Date: August 2023

Understand how we build parks.

Funding

Total Funding: $446,000
Funding Source: Mayoral

Location

Concrete Plant Park, Bronx
Edgewater Road between Bruckner Boulevard & Westchester Avenue
Community Board: 02

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024