Concrete Plant Park Emergency Tower Demolition
-
100% complete
-
100% complete
-
100% complete
This project will demolish three decommissioned concrete plant towers that have deteriorated and pose a public safety risk.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2023
Projected Completion Date:
November 2023
Completion Date:
October 2023
Procurement
Start Date: October 2023
Projected Completion Date:
October 2024
Completion
Date:
January 2024
Construction
Start Date: June 2023
Projected Completion Date:
September 2023
Completion Date: August 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Concrete Plant Park, Bronx
Edgewater Road between Bruckner Boulevard & Westchester Avenue
Community Board: 02
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025