Citywide Tree Guard Installation Contract FY24 (CNYG-1420MR)
-
100% complete
-
100% complete
-
0% complete
This project will install tree guard citywide.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2023
Projected Completion Date:
October 2023
Completion Date:
August 2023
Procurement
Start Date: August 2023
Completion
Date:
April 2024
Construction
Start Date: September 2023
Projected Completion Date:
September 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Last updated: 11/22/2024