J. Hood Wright Park Retaining Wall and Pedestrian Ramp Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct a retaining wall and pedestrian ramp at J. Hood Wright Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2021
Projected Completion Date: May 2022
Completion Date: November 2023

Procurement

Start Date: November 2023
Projected Completion Date: July 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

J. Hood Wright Park, Manhattan
South Pinehurst Avenue at West 176th Street
Community Board: 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024