Bronx and Manhattan Retaining Wall Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct retaining walls at various parks in The Bronx and Manhattan.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2021
Projected Completion Date: June 2022
Completion Date: June 2023

Procurement

Start Date: June 2023
Projected Completion Date: June 2024
Adjusted Completion Date: April 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Locations

  • Bronx River Parkway, Bronx
    Lafayette Avenue, Bronx Park, Burke Avenue, City Line
    Community Board: 06, 09, 12
  • Inwood Hill Park, Manhattan
    Dyckman Street, Hudson River, Harlem River Ship Canal
    Community Board: 12
  • Isham Park, Manhattan
    Broadway, Isham Street, Inwood Park
    Community Board: 12
  • Dorothy K. McGowan Memorial Garden, Manhattan
    West 158 Street between Amsterdam Avenue and Broadway
 