St. Nicholas Park 136th Street Staircase Reconstruction

  • Design
    0% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct a staircase in St. Nicholas Park.

Project Notes

Project Update: A meeting was held with stakeholders to discuss the scope of work for the project. Parks is now reviewing feedback from the meeting and the scope of work to determine the schedule for the project.

Project Timeline

Design

Assigned & Start Date: February 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

St. Nicholas Park, Manhattan
St. Nicholas Avenue and 136th Street
Community Board: 09

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024