Riverside Park Soldiers' and Sailors' Monument Restoration

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will restore the Soldiers' and Sailors' Monument in Riverside Park.

Project Notes

Project Update: The schematic design for this project has been approved. Parks is now developing the documents required to build this project.

Project Timeline

Design

Assigned & Start Date: December 2023
Projected Completion Date: June 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

Riverside Park, Manhattan
Riverside Park at West 89th street
Community Board: 07, 09

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024