Bushwick Inlet Park Sewer Connection Construction
-
100% complete
-
100% complete
-
0% complete
This project will install a sewer connection in Bushwick Inlet Park.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2023
Projected Completion Date:
February 2024
Completion Date:
July 2023
Procurement
Start Date: July 2023
Projected Completion Date:
July 2024
Completion
Date:
January 2025
Construction
Start Date: April 2025
Projected Completion Date:
October 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Bushwick Inlet Park, Brooklyn
Kent Avenue between N.12th and N.11th Streets
Community Board: 01
Project Staff
Project Liaison: James Morris
Contact NYC Parks
about this project
Last updated: 03/28/2025