Bushwick Inlet Park Sewer Connection Construction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will install a sewer connection in Bushwick Inlet Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2023
Projected Completion Date: February 2024
Completion Date: July 2023

Procurement

Start Date: July 2023
Projected Completion Date: July 2024
Adjusted Completion Date: September 2024

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Bushwick Inlet Park, Brooklyn
Kent Avenue between N.12th and N.11th Streets
Community Board: 01

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024