Bushwick Inlet Park Sewer Connection Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will install a sewer connection in Bushwick Inlet Park.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2023
Projected Completion Date: February 2024
Completion Date: July 2023

Procurement

Start Date: July 2023
Projected Completion Date: July 2024
Completion Date: January 2025

Construction

Start Date: April 2025
Projected Completion Date: October 2025

Understand how we build parks.

Funding

Total Funding: $1,176,000
Funding Source: Mayoral

Location

Bushwick Inlet Park, Brooklyn
Kent Avenue between N.12th and N.11th Streets
Community Board: 01

 

Project Staff

Project Liaison: James Morris
Contact NYC Parks about this project

Last updated: 03/28/2025