Zimmerman Playground Public Restroom Building Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roof of the public restroom building in Zimmerman Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2016
Projected Completion Date: July 2016
Completion Date: November 2016

Procurement

Start Date: August 2016
Projected Completion Date: January 2017
Completion Date: November 2016

Construction

Start Date: December 2016
Projected Completion Date: April 2017
Completion Date: April 2017

Understand how we build parks.

Funding

Total Funding: $76,000
Funding Source: Mayoral

Location

Zimmerman Playground, Bronx

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project