Zimmerman Playground Public Restroom Building Roof Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the roof of the public restroom building in Zimmerman Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2016
Projected Completion Date:
July 2016
Completion Date:
November 2016
Procurement
Start Date: August 2016
Projected Completion Date:
January 2017
Completion
Date:
November 2016
Construction
Start Date: December 2016
Projected Completion Date:
April 2017
Completion Date: April 2017
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Zimmerman Playground, Bronx
Project Staff
Project Liaison: Cristin Leoutsakos