Bronx and Manhattan Tree-Damaged Sidewalk Reconstruction FY23

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct sidewalks damaged by adjacent city-owned trees in Bronx and Manhattan.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2023
Projected Completion Date: December 2023
Completion Date: June 2023

Procurement

Start Date: June 2023
Projected Completion Date: June 2024
Completion Date: June 2024

Construction

Start Date: August 2024
Projected Completion Date: August 2026

Understand how we build parks.

Funding

Total Funding: $3,705,000
Funding Sources:
  • City Council
  • Mayoral

Location

Various locations, Bronx and Manhattan

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024