Staten Island Tree-Damaged Sidewalk Reconstruction FY23

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    7% complete

This project will reconstruct sidewalks damaged by adjacent city-owned trees in Staten Island.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2023
Projected Completion Date: December 2023
Completion Date: June 2023

Procurement

Start Date: June 2023
Projected Completion Date: June 2024
Completion Date: June 2024

Construction

Start Date: July 2024
Projected Completion Date: July 2026

Understand how we build parks.

Funding

Total Funding: $4,899,000
Funding Source: Mayoral

Location

Various locations, Staten Island

Project Staff

Contact NYC Parks about this project

Last updated: 01/17/2025