Queens Tree-Damaged Sidewalk Reconstruction FY23 Community Boards 3 & 4

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct sidewalks damaged by adjacent city-owned trees in Community Boards 3 and 4 in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2023
Projected Completion Date: December 2023
Completion Date: June 2023

Procurement

Start Date: June 2023
Projected Completion Date: June 2024
Completion Date: June 2024

Construction

Start Date: August 2024
Projected Completion Date: August 2025

Understand how we build parks.

Funding

Total Funding: $1,000,000
Funding Source: Mayoral

Location

Various locations, Queens

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024