Brooklyn Tree-Damaged Sidewalk Reconstruction FY23 Community Boards 1, 2, 6, 7, 10-14

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct sidewalks damaged by adjacent city-owned trees in Community Boards 1, 2, 6, 7, 10, 11, 12, 13 and 14 in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2023
Projected Completion Date: December 2023
Completion Date: June 2023

Procurement

Start Date: June 2023
Projected Completion Date: May 2024
Adjusted Completion Date: December 2024

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million

Location

Various locations, Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024