Queens Tree-Damaged Sidewalk Reconstruction Community Boards 12-14 (QG-1323MR)
-
100% complete
-
100% complete
-
88% complete
This project will reconstruct sidewalks damaged by adjacent city-owned trees in Community Boards 12-14.
Project Notes
Project Update: This project is in active construction.
Project Timeline
Design
Assigned & Start Date:
Procurement
Start Date:
Completion
Date:
October 2022
Construction
Start Date: January 2022
Projected Completion Date:
January 2024