Frederick Douglass Playground Reconstruction
-
5% complete
-
0% complete
-
0% complete
This project will reconstruct the Frederick Douglass Playground.
Project Notes
Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.
Project Timeline
Design
Assigned & Start Date: April 2024
Projected Completion Date:
April 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Frederick Douglass Playground, Manhattan
Amsterdam Ave between W.100 St. and W 102 St.
Community Board: 07
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024