Father Macris Park and Irving Square Park Compact Prefabricated Public Restroom Buildings Construction
-
100% complete
-
100% complete
-
47% complete
This project will construct compact prefabricated public restroom buildings at Father Macris Park and Irving Square Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2023
Projected Completion Date:
September 2023
Completion Date:
July 2023
Procurement
Start Date: July 2023
Projected Completion Date:
July 2024
Completion
Date:
May 2024
Construction
Start Date: May 2024
Projected Completion Date:
January 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Father Macris Park, Staten Island
Southside of Staten Island Expressway, Fahy Avenue, Lamberts Lane
Community Board: 02 -
Irving Square Park, Brooklyn
Wilson Avenue, Knickerbocker Avenue, between Halsey Street and Weirfield Street
Community Board: 04
Project Staff
Project Liaison: Contact Us
Contact NYC Parks
about this project
Last updated: 11/22/2024