Father Macris Park and Irving Square Park Compact Prefabricated Public Restroom Buildings Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    44% complete

This project will construct compact prefabricated public restroom buildings at Father Macris Park and Irving Square Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2023
Projected Completion Date: September 2023
Completion Date: July 2023

Procurement

Start Date: July 2023
Projected Completion Date: July 2024
Completion Date: May 2024

Construction

Start Date: May 2024
Projected Completion Date: January 2025

Understand how we build parks.

Funding

Total Funding: $2,601,000
Funding Source: Mayoral

Locations

  • Father Macris Park, Staten Island
    Southside of Staten Island Expressway, Fahy Avenue, Lamberts Lane
    Community Board: 02
  • Irving Square Park, Brooklyn
    Wilson Avenue, Knickerbocker Avenue, between Halsey Street and Weirfield Street
    Community Board: 04
 