D'Emic Playground Reconstruction

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

The project will reconstruct D'Emic Playground.

Project Notes

Project Update: Design is complete and permitting and legal review of the contract are in progress.

Project Timeline

Design

Assigned & Start Date: June 2023
Projected Completion Date: October 2024
Completion Date: October 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

D'Emic Playground, Brooklyn
3 Avenue between 35 Street and 34 Street
Community Board: 07

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024