Queens Tree-Damaged Sidewalk Reconstruction FY23 - Community Boards 1, 2, 5 ,6, 7, 8

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    23% complete

This project will reconstruct sidewalks damaged by adjacent city-owned trees in Community Boards 1, 2, 5 ,6, 7 and 8 in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2023
Projected Completion Date: December 2023
Completion Date: June 2023

Procurement

Start Date: June 2023
Projected Completion Date: June 2024
Completion Date: June 2024

Construction

Start Date: July 2024
Projected Completion Date: June 2026

Understand how we build parks.

Funding

Total Funding: $5,275,000
Funding Sources:
  • City Council
  • Mayoral

Location

Various Locations, Queens

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024