Brooklyn Tree-Damaged Sidewalk Reconstruction FY23 - Community Boards 3, 4, 5, 8, 9, 15, 16, 17, 18
-
100% complete
-
100% complete
-
37% complete
This project will reconstruct sidewalks damaged by adjacent city-owned trees in Community Boards 3, 4, 5, 8, 9, 15, 16, 17 and 18 in Brooklyn.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2023
Projected Completion Date:
December 2023
Completion Date:
June 2023
Procurement
Start Date: June 2023
Projected Completion Date:
June 2024
Completion
Date:
June 2024
Construction
Start Date: May 2024
Projected Completion Date:
May 2026
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Last updated: 01/17/2025