Joyce Kilmer Park, Hoyt Playground, and Thomas Jefferson Park Compact Prefabricated Public Restroom Buildings Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    6% complete

This project will construct compact prefabricated public restroom buildings at Joyce Kilmer Park, Hoyt Playground, and Thomas Jefferson Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2023
Projected Completion Date: September 2023
Completion Date: July 2023

Procurement

Start Date: July 2023
Projected Completion Date: July 2024
Completion Date: May 2024

Construction

Start Date: May 2024
Projected Completion Date: May 2025

Understand how we build parks.

Funding

Total Funding: $4,011,000
Funding Source: Mayoral

Locations

  • Hoyt Playground, Queens
    Hoyt Avenue, 29 to 31 Streets
    Community Board: 01
  • Joyce Kilmer Park, Bronx
    Walton Avenue between East 161 Street and East 164 Street, Grand Concourse
    Community Board: 04
  • Thomas Jefferson Park, Manhattan
    1st Avenue to FDR Drive, East 111 to East 114 Streets
    Community Board: 11
 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 11/22/2024