Joyce Kilmer Park, Hoyt Playground, and Thomas Jefferson Park Compact Prefabricated Public Restroom Buildings Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    35% complete

This project will construct compact prefabricated public restroom buildings at Joyce Kilmer Park, Hoyt Playground, and Thomas Jefferson Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2023
Projected Completion Date: September 2023
Completion Date: July 2023

Procurement

Start Date: July 2023
Projected Completion Date: July 2024
Completion Date: May 2024

Construction

Start Date: May 2024
Projected Completion Date: May 2025

Understand how we build parks.

Funding

Total Funding: $4,011,000
Funding Source: Mayoral

Locations

  • Hoyt Playground, Queens
    Hoyt Avenue, 29 to 31 Streets
    Community Board: 01
  • Joyce Kilmer Park, Bronx
    Walton Avenue between East 161 Street and East 164 Street, Grand Concourse
    Community Board: 04
  • Thomas Jefferson Park, Manhattan
    1st Avenue to FDR Drive, East 111 to East 114 Streets
    Community Board: 11
 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 01/17/2025