Sunset Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground in Sunset Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2011
Projected Completion Date: December 2012
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date: September 2014
Completion Date: October 2015

Construction

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: July 2017

Understand how we build parks.

Funding

Total Funding: $3,207,000
Funding Sources:
  • City Council
  • Mayoral

Location

Sunset Park, Brooklyn
6th Avenue at 44th Street
Community Board: 07

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025