Shore Front Parkway Roller Hockey Rink Reconstruction
-
5% complete
-
0% complete
-
0% complete
This project will reconstruct the roller hockey rink along Shore Front Parkway at Rockaway Beach.
Project Notes
Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.
Project Timeline
Design
Assigned & Start Date: November 2023
Projected Completion Date:
May 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Rockaway Beach Boardwalk, Queens
Shore Front Parkway at Beach 109th Street
Community Board: 14