Citywide Seawall Reconstruction

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct seawalls in various locations, citywide.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2019
Projected Completion Date: December 2023
Completion Date: June 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Locations

  • Belt Parkway/Shore Parkway, Brooklyn
    Belt Parkway between Verrazano Bridge and Cross Bay Boulevard
    Community Board: 05, 10, 11, 13, 15, 18, 10
  • Faber Pool and Park, Staten Island
    Richmond Terrace & Faber Street
    Community Board: 01
  • Whitey Ford Field, Queens
    1 & 2 Street, 26 Avenue & East River
    Community Board: 01
 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 11/22/2024