North Rochdale Playground Reconstruction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct North Rochdale playground.

Project Notes

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Assigned & Start Date: July 2023
Projected Completion Date: February 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: City Council

Location

North Rochdale Playground, Queens
Baisley Boulevard 168th Street and Bedell Street
Community Board: 12

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024