Bath Beach Park Synthetic Turf Field Construction
-
100% complete
-
0% complete
-
0% complete
This project will construct the synthetic turf field at Bath Beach Park.
Project Notes
Project Update: Design is complete and permitting and legal review of the contract are in progress.
Project Timeline
Design
Assigned & Start Date: May 2023
Projected Completion Date:
September 2024
Completion Date:
August 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Bath Beach Park, Brooklyn
Shore Parkway to Bay 16th Street
Community Board: 11
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024