Maria Hernandez Park Playground and Dog Run Reconstruction

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the playground and dog run in Maria Hernandez Park.

Project Notes

Project Update: The schematic design for this project has been approved. Parks is now developing the documents required to build this project.

Project Timeline

Design

Assigned & Start Date: June 2023
Projected Completion Date: January 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: City Council

Location

Maria Hernandez Park, Brooklyn
Irving Avenue, Knickerbocker Avenue between Starr Street and Suydam Street
Community Board: 04

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024