Commodore Barry Park Multipurpose Play Area Reconstruction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the multipurpose play area at Commodore Barry Park.

Project Notes

Project Update: All contract documents are now in final review to complete the design process.

Project Timeline

Design

Assigned & Start Date: December 2023
Projected Completion Date: March 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

Commodore Barry Park, Brooklyn
Flushing Avenue between Navy Street and North Elliot Place
Community Board: 02

 

Project Staff

Project Liaison: James Morris
Contact NYC Parks about this project

Last updated: 03/28/2025