Riverside Park 91st Street Staircase Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the staircase at Riverside Park 91st Street.

Project Notes

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2023
Projected Completion Date: April 2024
Completion Date: May 2024

Procurement

Start Date: May 2024
Projected Completion Date: May 2025
Adjusted Completion Date: November 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: City Council

Location

Riverside Park, Manhattan
Riverside Park at West 91st Street.
Community Board: 07, 09

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 04/25/2025