Fort Washington Park Lily Brown Playground Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct Lily Brown Playground in Fort Washington Park .

Project Notes

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2023
Projected Completion Date: January 2024
Completion Date: January 2024

Procurement

Start Date: January 2024
Projected Completion Date: January 2025
Adjusted Completion Date: May 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: City Council

Location

Fort Washington Park, Manhattan
163rd Street and Riverside Drive
Community Board: 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025