Fort Washington Park Lily Brown Playground Reconstruction
-
100% complete
-
60% complete
-
0% complete
This project will reconstruct Lily Brown Playground in Fort Washington Park .
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2023
Projected Completion Date:
January 2024
Completion Date:
January 2024
Procurement
Start Date: January 2024
Projected Completion Date:
January 2025
Adjusted Completion
Date:
May 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Fort Washington Park, Manhattan
163rd Street and Riverside Drive
Community Board: 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024