Sol Bloom Playground Reconstruction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Sol Bloom Playground.

Project Notes

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Assigned & Start Date: November 2023
Projected Completion Date: November 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: City Council

Location

Sol Bloom Playground, Manhattan
West 91st Street and West 92nd Street between Columbus Avenue and Central Park West
Community Board: 07

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024