Cadman Plaza Park Brooklyn War Memorial ADA Ramp and Elevator Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install an accessible ramp and elevator at the Brooklyn War Memorial in Cadman Plaza Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2016
Projected Completion Date: June 2017
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: May 2018
Completion Date: July 2019

Construction

Start Date: January 2020
Projected Completion Date: January 2021
Completion Date: October 2021

Understand how we build parks.

Funding

Total Funding: $3,889,000
Funding Sources:
  • Borough President
  • City Council
  • Federal
  • Mayoral

Location

Cadman Plaza Park, Brooklyn
Cadman Plaza West, Tillary Street, Cadman Plaza East, Tillary Street, Brooklyn Bridge
Community Board: 02

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025