Dr. Charles Drew Park Natural Turf Field Reconstruction
-
35% complete
-
0% complete
-
0% complete
This project will reconstruct the natural turf fields, security lighting and sidewalks at Dr. Charles Drew Park.
Project Notes
Project Update: The schematic design for this project has been approved. Parks is now developing the documents required to build this project.
Project Timeline
Design
Assigned & Start Date: September 2023
Projected Completion Date:
April 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Dr. Charles R. Drew Park, Queens
Between Van Wyck Expressway Sr. Road East, 140th Street, 115th and 116th Avenues
Community Board: 12
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025