Uncle Vito F. Maranzano Glendale Playground Reconstruction

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Uncle Vito F. Maranzano Glendale Playground.

Project Notes

Project Update: Design is complete and permitting and legal review of the contract are in progress.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2023
Projected Completion Date: October 2024
Completion Date: February 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: City Council

Location

"Uncle" Vito F. Maranzano Glendale Playground, Queens
Central Avenue between 70th and 71st Street
Community Board: 05

 

Project Staff

Project Liaison: Meira Berkower