Virginia Principe Playground Reconstruction
-
5% complete
-
0% complete
-
0% complete
This project will reconstruct Virginia Principe Park Playground.
Project Notes
Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.
Project Timeline
Design
Assigned & Start Date: April 2024
Projected Completion Date:
June 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Frank Principe Park, Queens
Maurice Avenue and 63rd street between 54th Avenue and Borden Avenue
Community Board: 05
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024