Annadale Green Reconstruction
-
100% complete
-
85% complete
-
0% complete
This project will reconstruct the passive park and sidewalks at Annadale Green.
Project Notes
Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.
Project Timeline
Design
Assigned & Start Date: January 2023
Projected Completion Date:
January 2024
Completion Date:
January 2024
Procurement
Start Date: January 2024
Projected Completion Date:
September 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Annadale Green, Staten Island
Jefferson Boulevard and Annadale Road
Community Board: 03
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 02/21/2025