Annadale Green Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the passive park and sidewalks at Annadale Green.

Project Notes

Project Update: The project has entered procurement and is being reviewed and prepared for solicitation.

Project Timeline

Design

Assigned & Start Date: January 2023
Projected Completion Date: January 2024
Completion Date: January 2024

Procurement

Start Date: January 2024
Projected Completion Date: September 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Borough President
  • City Council

Location

Annadale Green, Staten Island
Jefferson Boulevard and Annadale Road
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 10/11/2024