Ferry Point Park Golf Course Parking Lot Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install new pavement at the lower parking lot at the Ferry Point Park Golf Course.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2014
Projected Completion Date: January 2015
Completion Date: January 2015

Procurement

Start Date: March 2015
Projected Completion Date: August 2015
Completion Date: March 2015

Construction

Start Date: April 2015
Projected Completion Date: June 2015
Completion Date: May 2015

Understand how we build parks.

Funding

Total Funding: $391,000
Funding Source: Mayoral

Location

Ferry Point Park, Bronx

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024