Midland Playground Reconstruction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the playground area in Midland Playground.

Project Notes

Project Update: All contract documents are now in final review to complete the design process.

Project Timeline

Design

Assigned & Start Date: May 2023
Projected Completion Date: November 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Borough President
  • City Council

Location

Midland Playground, Staten Island
Midland Avenue, Lincoln Avenue, and Oldfield Street
Community Board: 02

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024