Midland Playground Reconstruction
-
90% complete
-
0% complete
-
0% complete
This project will reconstruct the playground area in Midland Playground.
Project Notes
Project Update: All contract documents are now in final review to complete the design process.
Project Timeline
Design
Assigned & Start Date: May 2023
Projected Completion Date:
November 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Midland Playground, Staten Island
Midland Avenue, Lincoln Avenue, and Oldfield Street
Community Board: 02
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024