Givans Creek Woods Park Pathway Construction

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a pathway at Givans Creek Woods Park.

Project Notes

Project Update: Parks is continuing to develop the documents to build this project.

Project Timeline

Design

Assigned & Start Date: April 2024
Projected Completion Date: July 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

Givans Creek Woods, Bronx
Co-op City Boulevard between Baychester Avenue and Dreiser Loop
Community Board: 10

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 02/21/2025