Givans Creek Woods Park Pathway Construction

  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a pathway at Givans Creek Woods Park.

Project Notes

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

Project Timeline

Design

Assigned & Start Date: April 2024
Projected Completion Date: July 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

Givans Creek Woods, Bronx
Co-op City Boulevard between Baychester Avenue and Dreiser Loop
Community Board: 10

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024