Givans Creek Woods Park Pathway Construction
-
50% complete
-
0% complete
-
0% complete
This project will construct a pathway at Givans Creek Woods Park.
Project Notes
Project Update: Parks is continuing to develop the documents to build this project.
Project Timeline
Design
Assigned & Start Date: April 2024
Projected Completion Date:
July 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Givans Creek Woods, Bronx
Co-op City Boulevard between Baychester Avenue and Dreiser Loop
Community Board: 10
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 02/21/2025