Givans Creek Woods Park Pathway Construction
-
30% complete
-
0% complete
-
0% complete
This project will construct a pathway at Givans Creek Woods Park.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
Project Timeline
Design
Assigned & Start Date: April 2024
Projected Completion Date:
July 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Givans Creek Woods, Bronx
Co-op City Boulevard between Baychester Avenue and Dreiser Loop
Community Board: 10
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024