Staten Island Street Tree Planting FY23

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will plant new and replacement trees in Staten Island.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2022
Projected Completion Date: March 2023
Completion Date: January 2023

Procurement

Start Date: January 2023
Projected Completion Date: October 2023
Adjusted Completion Date: December 2024

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • Private

Location

Various locations

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024