Marconi Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground, spray shower and seating area in Marconi Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2012
Projected Completion Date: February 2013
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date: September 2014
Completion Date: April 2015

Construction

Start Date: June 2015
Projected Completion Date: June 2016
Completion Date: June 2016

Understand how we build parks.

Funding

Total Funding: $1,901,000
Funding Sources:
  • Borough President
  • Mayoral

Location

Marconi Park, Queens
155th Street and 109th Avenue, Queens
Community Board: 12

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025