Queens PLANYC Street Tree Planting FY23 - Community Boards 6, 9 & 10

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    47% complete

This project will plant new and replacement trees in Community Boards 6, 9 & 10 in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2022
Projected Completion Date: March 2023
Completion Date: January 2023

Procurement

Start Date: January 2023
Projected Completion Date: October 2023
Completion Date: March 2024

Construction

Start Date: March 2024
Projected Completion Date: March 2025

Understand how we build parks.

Funding

Total Funding: $2,760,000
Funding Source: Mayoral

Location

Various locations

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024