Queens Street Tree Planting FY23 - Community Boards 1-5

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will plant new and replacement trees in Community Boards 1-5 in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2022
Projected Completion Date: March 2023
Completion Date: January 2023

Procurement

Start Date: January 2023
Projected Completion Date: October 2023
Completion Date: July 2024

Construction

Start Date: August 2024
Projected Completion Date: August 2026

Understand how we build parks.

Funding

Total Funding: $7,120,000
Funding Sources:
  • Mayoral
  • Private

Location

Various locations

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024