Brooklyn Street Tree Planting FY23 - Community Boards 11, 13 & 15

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will plant new and replacement trees in Community Boards 11, 13 & 15 in Brooklyn.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2022
Projected Completion Date: March 2023
Completion Date: January 2023

Procurement

Start Date: January 2023
Projected Completion Date: October 2023
Completion Date: June 2024

Construction

Start Date: August 2024
Projected Completion Date: August 2025

Understand how we build parks.

Funding

Total Funding: $3,540,000
Funding Sources:
  • Mayoral
  • Private

Location

Various locations

Project Staff

Contact NYC Parks about this project

Last updated: 01/17/2025