Brooklyn Street Tree Planting FY23 - Community Boards 5 & 16
-
100% complete
-
5% complete
-
0% complete
This project will plant new and replacement trees in Community Boards 5 & 16 in Brooklyn.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2022
Projected Completion Date:
March 2023
Completion Date:
January 2023
Procurement
Start Date: January 2023
Projected Completion Date:
October 2023
Adjusted Completion
Date:
August 2024
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Last updated: 11/22/2024