Brooklyn Street Tree Planting FY23 - Community Boards 1, 2 & 6
-
100% complete
-
100% complete
-
29% complete
This project will plant new and replacement trees in Community Boards 1, 2 and 6 in Brooklyn.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2022
Projected Completion Date:
March 2023
Completion Date:
January 2023
Procurement
Start Date: January 2023
Projected Completion Date:
October 2023
Completion
Date:
March 2024
Construction
Start Date: April 2024
Projected Completion Date:
March 2025
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Private
Last updated: 11/22/2024