Von Dohlen Playground Adult Fitness and Skate Area Construction and Ballfield Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the asphalt ballfield and construct an adult fitness and skate area in Von Dohlen Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2012
Projected Completion Date:
July 2013
Completion Date:
January 2014
Procurement
Start Date: January 2014
Projected Completion Date:
October 2014
Completion
Date:
January 2015
Construction
Start Date: May 2015
Projected Completion Date:
April 2016
Completion Date: April 2016
Understand how we build parks.
Funding
Funding Source: Borough President
Location
Howard Von Dohlen Playground, Queens
Archer Avenue and 91st Avenue,138th Street and 138th Place, Queens
Community Board: 12
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project