Von Dohlen Playground Adult Fitness and Skate Area Construction and Ballfield Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the asphalt ballfield and construct an adult fitness and skate area in Von Dohlen Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2012
Projected Completion Date: July 2013
Completion Date: January 2014

Procurement

Start Date: January 2014
Projected Completion Date: October 2014
Completion Date: January 2015

Construction

Start Date: May 2015
Projected Completion Date: April 2016
Completion Date: April 2016

Understand how we build parks.

Funding

Total Funding: $1,100,000
Funding Source: Borough President

Location

Howard Von Dohlen Playground, Queens
Archer Avenue and 91st Avenue,138th Street and 138th Place, Queens
Community Board: 12

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024