Queens Park Tree Planting FY23

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will plant new and replacement park trees in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2022
Projected Completion Date: March 2023
Completion Date: March 2023

Procurement

Start Date: March 2023
Projected Completion Date: February 2024
Completion Date: November 2024

Construction

Start Date: November 2024
Projected Completion Date: November 2025

Understand how we build parks.

Funding

Total Funding: $1,090,000
Funding Sources:
  • Mayoral
  • Private

Location

Various park locations

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024