Willis Playground Public Restroom Building Roof Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the roof of the public restroom building in Willis Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2015
Projected Completion Date:
February 2016
Completion Date:
December 2015
Procurement
Start Date: April 2016
Projected Completion Date:
September 2016
Completion
Date:
June 2016
Construction
Start Date: September 2016
Projected Completion Date:
October 2016
Completion Date: October 2016
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Willis Playground, Bronx
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025