Queens Street Tree Planting FY23 - Community Board 7 (QG-1019MR)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new trees in Community Board 7 in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2022
Projected Completion Date: December 2022
Completion Date: September 2022

Procurement

Start Date: September 2022
Completion Date: April 2023

Construction

Start Date: October 2022
Projected Completion Date: May 2023
Completion Date: July 2023

Understand how we build parks.

Funding

Total Funding: $900,000
Funding Sources:
  • Mayoral
  • Private

Location

Various locations

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024