Osborn Playground Adult Fitness Construction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will construct an adult fitness area at Osborn Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2022
Projected Completion Date: November 2023
Completion Date: September 2023

Procurement

Start Date: September 2023
Projected Completion Date: September 2024
Adjusted Completion Date: June 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Osborn Playground, Brooklyn
Linden Boulevard and Osborn Street
Community Board: 16

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024