Commodore Barry Park Pool Deck Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the pool deck in Commodore Barry Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2016
Projected Completion Date:
March 2016
Completion Date:
September 2016
Procurement
Start Date: April 2016
Projected Completion Date:
September 2016
Completion
Date:
September 2016
Construction
Start Date: December 2016
Projected Completion Date:
June 2017
Completion Date: June 2017
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Commodore Barry Park, Brooklyn
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks